REPORT TO COUNCIL
SUBJECT
Title
Approval of the 2020 Sewer System Management Plan (SSMP)
BACKGROUND
On May 2, 2006, the State Water Resources Control Board (Board) adopted Order No. 2006-0003 - Statewide General Waste Discharge Requirements (GWDR) for Sanitary Sewer Systems. The Order requires public agencies that own or operate sanitary sewer systems to develop and implement a SSMP aimed at reducing sanitary sewer overflows (SSOs). It also requires these agencies to report all SSOs to the Board. The SSMP must include 11 elements demonstrating how the agency constructs, manages, operates and maintains its sanitary sewer system. These elements are described in the attached revised SSMP and are summarized below:
1. Goals of the SSMP
2. Organization and chain of communications for the SSMP
3. Legal Authority to operate and maintain its sewage collection system
4. Sewer Collection System Operation & Maintenance Program
5. Sewer Collection System Design and Performance Provisions
6. Sewer Overflow Emergency Response Plan
7. Fats, Oil and Grease Control Program
8. Collection System Evaluation and Capacity Assurance Plan
9. Monitoring, Management and Plan Modifications
10. SSMP Program Audits
11. Communication Program with Public and Stakeholders
The Order requires that the governing body for each agency approve its agency’s SSMP at a public meeting. Council approved the 2015 SSMP on May 12, 2015 (RTC No. 15-0456).
The GWDR requires that the SSMP be updated and recertified at least every five years.
EXISTING POLICY
General Plan Goal EM-6: Effective Wastewater Collection System
Continue to operate and maintain the wastewater collection system so that all sewage and industrial wastes generated within the City are collected and conveyed under safe and sanitary conditions to the Water Pollution Control Plant.
ENVIRONMENTAL REVIEW
Implementation of the SSMP will apply to sanitary sewer collection systems that constitute "existing facilities" of the City, or may require the installation of minor sewer system facilities which will involve either minor alterations to existing facilities, or repair or replacement of existing facilities involving negligible or no expansion of sewer capacity. Such activities are exempt from review under the California Environmental Quality Act (CEQA). (CEQA Guidelines sections15301 and 15302.) The adoption of the SSMP is also exempt from environmental review because it requires the implementation of management operations programs and plans to enhance and protect the environment by limiting the occurrence of SSOs in the City. (CEQA Guideline section 15308.).
DISCUSSION
The goals of Sunnyvale’s SSMP are to:
• Reduce, prevent, and mitigate the impacts of SSOs.
• Provide adequate capacity to convey all flows, including peak flows.
• Be available and responsive to the needs of the public, and work cooperatively with local, state, and federal agencies to reduce, mitigate the impacts of, and properly report SSOs.
• Identify, prioritize, and continuously renew and replace sewer system facilities to maintain reliability.
• Implement regular, proactive maintenance of the system to remove roots, debris, and fats, oils and grease (FOG) in areas prone to blockages that may cause sewer backups or SSOs.
• Uphold Sunnyvale’s standards and specifications on newly constructed public and private sewers.
Sanitary sewers often contain high levels of pathogenic organisms and toxic pollutants. When overflows of the system occur, untreated sewage can flow into streets, onto properties, and through the storm drain system into local waterways. Consequently, SSOs have the potential to pollute surface water and groundwater, threaten public health, adversely affect aquatic life and impair the recreational use and aesthetic enjoyment of surface waters. There are many causes of SSOs. Some major causes of SSOs include grease and root blockages in sewer lines, sewer line damage, manhole structure failures, pump station outages or failures, excessive storm or ground water inflow and infiltration and sewer system aging. SSOs can be minimized with effective management, operations and maintenance of the sewer system.
The Environmental Services Department retained HydroScience Engineers to prepare the City’s 2020 SSMP (Attachment 1). The 2020 SSMP will be posted on the City’s website for public review.
Adoption of the 2020 SSMP will ensure that Sunnyvale is in compliance with the State Water Board’s requirement to update and recertify the SSMP at least every five years. Continued implementation and monitoring of the 2020 SSMP will facilitate proper management of the sanitary sewer system and help reduce sanitary sewer overflows.
FISCAL IMPACT
There are no fiscal impacts at this time. Approval of the revised SSMP does not require additional funding. However, additional funding may be required in the future as changes in the SSMP are developed by the City or directed by the Board. For example, the Board may determine that an increase in sewer pipe cleaning frequencies is necessary, and therefore, additional maintenance resources are needed. Any additional funding needs as a result of changes in the SSMP will be quantified and brought forward during future budget processes.
PUBLIC CONTACT
Public contact was made by posting the Council agenda on the City's official-notice bulletin board outside City Hall, Sunnyvale Public Library and Department of Public Safety; and by making the agenda and report available at the Sunnyvale Public Library, the Office of the City Clerk and on the City's website.
RECOMMENDATION
Recommendation
Approve the 2020 Sewer System Management Plan to meet State Water Board requirements.
Staff
Prepared by: Mansour Nasser, Water & Sewer Systems Division Manager
Reviewed by: Ramana Chinnakotla, Director, Environmental Services Department
Reviewed by: Jaqui Guzmán, Deputy City Manager
Approved by: Kent Steffens, City Manager
ATTACHMENTS
1. 2020 Sanitary Sewer Master Plan