Title: Quarter One Update for Year 2 of July 2025 - June 2027 Workplan (Information Only)
Attachments: 1. Attachment 1 Workplan Dashboard.pdf, 2. Attachment 2 List of Completed Projects.pdf

REPORT TO COUNCIL

SUBJECT

Title

Quarter One Update for Year 2 of July 2025 - June 2027 Workplan (Information Only)

 

Report

BACKGROUND

In early 2025, Council set five (5) strategic goals to guide the City from July 2025 through June 2027. In the next two years, we are taking active steps to create:

 

1.                     A responsive, transparent, and efficient city government;

2.                     An accessible, engaged and welcoming community;

3.                     A sustainable city: advancing climate action, active transportation and the Vision Zero Plan;

4.                     A model to prevent homelessness, prioritize new housing, and support the unhoused community; and

5.                     A City that invests in modern public infrastructure.

 

Staff developed a two-year Workplan associated with the Strategic Goals, and provides quarterly updates on Workplan progress. This report provides Workplan Updates from the first quarter for FY2026/27 (July - September 2026).

 

EXISTING POLICY

General Plan, Chapter 2: Community Vision

 

DISCUSSION

The Strategic Framework Workplan serves as a comprehensive list of priority initiatives requiring significant staff resources during the July 2025 through June 2027 period. It includes efforts to implement Council-adopted and State-mandated plans (such as the Housing Element, Active Transportation Plan, and Climate Action Playbook), major capital improvement projects, Council Priority Projects, and other substantial initiatives that require focused attention or enhanced staff capacity over the two-year timeframe.

 

The Workplan is intentionally limited to significant efforts that directly support the Council’s Strategic Goals. It does not capture the City’s day-to-day operations and service delivery, which are reported separately on an annual basis and documented through performance measures and workload indicators in the City’s adopted budget.

 

Workplan Changes During Q1 FY2026-2027 (July - September 2026)

During the first quarter, the City Manager made the following changes to the Workplan:

 

The City Manager added the following operational project:

•                     CO-31: Equity Implementation Plan

 

The City Manager removed the following project:

•                     IN-19: Producing Recycled Water with Package Plant

Rationale: The project was discontinued because the vendor had not received regulatory approval for the proposed equipment. In addition, the Secondary Treatment and Dewatering Project is nearing completion and, once operational, will enable the City to produce recycled water without this equipment. Therefore, staff elected not to proceed with the recycled water package plant.

 

The Workplan Dashboard includes project updates through Year 2 first-quarter (July - September 2026) and is available on the City's website under the “Your Government” section (Attachment 1).

 

Summary Update for Q1 FY2026-2027 (July - September 2026)

Staff continued to make progress advancing initiatives across all five Council Strategic Goals during the first quarter of FY2026/27. Across the Workplan, several projects reached completion, while the majority of active projects continued progressing toward their planned milestones. Some projects experienced schedule adjustments due to scope refinement, coordination needs, or resource constraints.

 

The following highlights provide a snapshot of notable progress on active projects across each Council Strategic Goal during Q1 FY2026/27, along with select significant developments through October 2026. Complete project details and status updates are available in the Workplan Dashboard online.

 

Responsive Government

Projects under the Responsive Government goal continued to advance operational efficiency, technology modernization, financial transparency, and accessibility. Council approved the vendor contract for the new Work Order Management System in September, with project planning underway. Staff also advanced Geographic Information Systems (GIS) improvements, including the launch of Active Transportation Plan and Capital Improvement Plan maps, and continued evaluating digital budget book software following publication of a Budget in Brief document. The City continued work on federal digital accessibility requirements, and staff is developing website governance practices. Public safety technology projects also moved forward, including review of the Computer Aided Dispatch system’s connectivity and integration requirements, and evaluation of a replacement Records Management System. Additional efforts included developing artificial intelligence governance tools, implementing data loss prevention policies, and reviewing proposals for a new Public Records Act and e-discovery tool.

 

Welcoming Community

Projects supporting the Welcoming Community goal continued to advance community engagement, inclusion, neighborhood improvements, and historic preservation during this quarter. Following completion of the Community Equity Assessment in August 2026, the City added an Equity Implementation Plan to the Workplan to guide the next phase of its equity efforts. Staff released a draft updated Historical Context Statement and continued work on the Japanese American incarceration memorial proposal. Heritage preservation efforts advanced through preparation of Heritage Resource Inventory hearings and development of the Heritage Plaque Program. Staff continued implementing public art programs and cultural inclusion activities, including summer outreach and community programming. Work also progressed on the community engagement platform procurement, language access and outreach initiatives, and neighborhood-serving retail implementation planning. Public Works reduced the sidewalk maintenance backlog from 5,040 to 2,051 locations, a 59% reduction, while continuing repairs.

 

Housing Solutions

Housing Solutions projects continued to focus on housing policy, zoning modernization, affordable housing opportunities, and resident protections during the first quarter. Following completion of the Homelessness Strategic Plan in September 2026, staff continued advancing initiatives to address homelessness and expand housing opportunities. Following Council direction, staff planned additional Tenant Protections Program outreach for fall 2026 through spring 2027. Staff advanced work on the new Housing Development Plan Review Permit, related zoning amendments, and potential changes to inclusionary housing requirements. Research continued on open space standards, adaptive reuse, development and impact fees, and park dedication fees. Staff also progressed work on affordable housing opportunities in high-resource areas, including a proposed Peery Park Specific Plan amendment, and prepared for a December workshop on missing-middle housing strategies. Age-friendly housing efforts included preparation of Housing Mitigation Fund recommendations and exploration of nonprofit partnerships. Several regulatory and fee studies remain delayed as staff complete analysis, outreach, and review processes.

 

Sustainable City

Projects supporting the Sustainable City goal continued to advance climate action, active transportation, resource conservation, and shoreline resilience during the first quarter. Staff tracked implementation of the six Climate Action Playbook strategies and prepared an annual progress report for Council. Work continued on the Lakewood Safe Routes to School project, with design complete and construction bidding planned for late 2026, and on pedestrian and school-route improvements in the SNAIL and Braly neighborhoods. Staff advanced environmental review for the Mary Avenue Overpass and coordination with Caltrans on the Stevens Creek Trail Extension. The City's multi-family FoodCycle outreach included approximately 2,000 door-to-door contacts, while planning continued for redesigned residential collection carts. Other active efforts included the SMaRT Station rebuild, signalization improvements, shoreline protection coordination, and ongoing Safe Routes to School programming.

 

Modern Infrastructure

Modern Infrastructure projects continued to advance major facilities, utilities, transportation, and technology investments during the first quarter. A significant milestone was achieved with the grand opening of the Lakewood Branch Library and Learning Center on October 31, 2026, expanding access to library services, educational resources, and community programming in north Sunnyvale. Construction also continued at Lakewood Park following the playground opening in July. Fire Station 2 advanced through final plan review and environmental work required for federal grant authorization before construction bidding. The Sunnyvale Clean Water Program continued construction of major treatment facilities and work on its Master Plan update, with Council consideration anticipated in early 2027. Staff also advanced cooperative and funding agreements for the Sunnyvale Avenue and Mary Avenue Caltrain grade separations, continued street resurfacing work, and prepared automated water meter infrastructure implementation planning. Technology projects included development of a cell coverage mapping tool and upgrades to network bandwidth and fire station alerting systems. Additional community engagement continued for the Las Palmas Park Renovation, while several projects remain on revised schedules.

 

Completed Projects

Staff completed 55 projects since Workplan development (including completions from July 2025-September 2026). Eleven (11) of the 55 projects completed were Council Priority Projects (formerly Study Issues). There are an additional five (5) projects with anticipated or actual completions in October 2026. These projects are outlined in Attachment 2.

 

The next quarterly update will be provided in January 2027.

 

PUBLIC CONTACT

Public contact was made by posting the Council meeting agenda on the City's official-notice bulletin board at City Hall, at the Sunnyvale Public Library and in the Department of Public Safety Lobby. In addition, the agenda and this report are available at the City Hall reception desk located on the first floor of City Hall at 456 W. Olive Avenue (during normal business hours), and on the City's website.

 

Staff

Prepared by: Michelle Zahraie, Senior Management Analyst

Reviewed by: Sarah Johnson-Rios, Assistant City Manager

Approved by: Tim Kirby, City Manager

 