Meeting Body: City Council
On agenda: 4/28/2020
Title: Award of Contract to V&A Consulting Engineers, Inc. for Design Services for the Cathodic Protection - Phase 1 Project (F18-149)
Attachments: 1. Draft Consultant Services Agreement, 2. Project 831840 - Cathodic Protection SFPUC Turnouts and Transmission Pipeline

REPORT TO COUNCIL

SUBJECT

Title

Award of Contract to V&A Consulting Engineers, Inc. for Design Services for the Cathodic Protection - Phase 1 Project (F18-149)

 

Report

REPORT IN BRIEF

Approval is requested to award a contract in the amount of $331,867 ($277,660 in base services and $54,207 in optional services) to V&A Consulting Engineers, Inc. of Oakland for design services for the Cathodic Protection - Phase 1 Project. Approval is also request for a 10% contingency in the amount of $33,187.

 

EXISTING POLICY

Pursuant to Chapter 2.08 of the Sunnyvale Municipal Code, contracts for this type of service are awarded pursuant to a Request for Proposals (RFP) best value process, unless otherwise exempt from the competitive bidding process. Additionally, City Council approval is required for the procurement of goods and/or services exceeding $100,000 in any one transaction.

 

ENVIRONMENTAL REVIEW

The action being considered does not constitute a “project” within the meaning of the California Environmental Quality Act (“CEQA”) pursuant to CEQA Guidelines section 15378(a) as it has no potential for resulting in either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment.

 

BACKGROUND AND DISCUSSION

Capital Improvement Project 831840 - Cathodic Protection SFPUC Turnouts and Transmission Pipeline, provides funding for corrosion protection at several locations in the City’s water transmission and distribution system.  The 2010 Water Utility Master Plan identified that the best means of corrosion protection is to implement a cathodic protection system. The current Phase 1 project will provide for design and construction of a cathodic protection system for six of the San Francisco Public Utilities Commission (SFPUC) water system connections and downstream transmission piping. A future phase will address 17 pipeline locations where metallic pipes cross major transportation corridors that are difficult to access.  As the City’s water system is a critical asset in the City’s infrastructure, the new cathodic system will provide protection from corrosion of these water pipelines, extend the service life, reduce the potential of a catastrophic pipeline failure, and reduce the maintenance costs associated with water leaks.

 

The SFPUC water system is the City’s main source of water and makes up fifty percent of the City’s water supply. 

 

A Request for Proposals (RFP) was posted on the City’s Demandstar public procurement network on November 2, 2017 and directly emailed to three bay area design consultant firms. A sole responsive and responsible proposal was received on November 16, 2017 from V&A Consulting Engineers, Inc (V&A Consulting). Staff from the Departments of Public Works and Environmental Services evaluated their proposal based on their demonstrated qualifications, experience, and programmatic approach.  The evaluation team unanimously agreed that V&A Consulting is qualified to perform this project.

 

The initial obstacle in proceeding with a timely award of this contract in early 2018 was cost, as the initial scope of work exceeded the budget by over $140,000. In subsequent discussions with the Consultant, it was determined that some preparation work could be done to the water system by City staff to simplify the scope, reducing the amount of work by the Consultant so the remaining scope would fit within the available budget. Considering the specialized nature of this work, and that only one proposal was received, the City, pursuant to Sunnyvale Municipal Code Section 2.08.120 (a), negotiated with V&A Consulting resulting in a simplified scope of work and overall approach that considers many value engineering options and still delivers the project objectives.  

 

Over the past 2 years, City Staff and V&A Consulting worked collaboratively to lay out a plan where the City performed some of the preliminary work with its own staff to reduce costs during design and construction. The preparation work performed by the City included installation of equipment on three of the six identified locations. City staff completed this work over several months, as time allowed, while they performed their normal duties.  After completion of work performed by the City, V&A Consulting provided an updated scope of work that included a complete cathodic protection design for the three locations and revised the cost proposal that totaled $331,867.00, which was almost half of the initial proposal and within the available budget. Optional services in the amount of $54,207 are included for additional field preparation of the three City-prepared sites and to develop future monitoring programs. Staff considers this to be a reasonable fee, appropriate for the specialized and complicated nature of the design work for this project.

 

FISCAL IMPACT

The contract consists of base services in the amount of $277,660, optional services in the amount of $54,207, and a 10% contingency in the amount of $33,187, for a total of $365,054. Funds are budgeted in Project 831840, Cathodic Protection SFPUC Turnouts and Transmission Pipeline, which the project has $877,886 available as carryover from prior year.

 

Funding Source

Funding for this project is budgeted in the Water Supply and Distribution Fund.

 

PUBLIC CONTACT

Public contact was made by posting the Council agenda on the City's official-notice bulletin board outside City Hall, Sunnyvale Public Library and Department of Public Safety; and by making the agenda and report available at the Office of the City Clerk and on the City's website.

 

 

RECOMMENDATION

Recommendation

Take the following actions:

-                     Award a contract in substantially the same form as Attachment 1 to the report in the amount of $331,867 to V&A Consulting Engineers, Inc.,

-                     Authorize the City Manager to execute the contract when all necessary conditions have been met, and

-                     Approve a 10% contingency in the amount of $33,187.

 

Staff

Prepared by:                      Gregory S. Card, Purchasing Officer

Reviewed by:                      Tim Kirby, Director of Finance

Reviewed by:                      Ramana Chinnakotla, Director of Environmental Services

Reviewed by:                      Chip Taylor, Director of Public Works

Reviewed by:                      Jaqui Guzmán, Deputy City Manager

Approved by:                      Kent Steffens, City Manager

 