Title: Adopt Resolution Authorizing the City Manager to Execute and Deliver an Installment Sale Agreement, for up to $288,000,000 in Clean Water State Revolving Funds, Between the City of Sunnyvale and the State Resources Water Control Board, and to Execute All Implementing Documents for Financial Assistance in Connection with the City's Water Pollution Control Plant Update Project
Attachments: 1. Resolution, 2. CWSRF Memorandum and Sample Agreement

REPORT TO COUNCIL

SUBJECT

Title

Adopt Resolution Authorizing the City Manager to Execute and Deliver an Installment Sale Agreement, for up to $288,000,000 in Clean Water State Revolving Funds, Between the City of Sunnyvale and the State Resources Water Control Board, and to Execute All Implementing Documents for Financial Assistance in Connection with the City’s Water Pollution Control Plant Update Project

 

Report

BACKGROUND

The City has embarked on the most significant single public works program in its history, the rebuild of its aged Water Pollution Control Plant (WPCP). The WPCP is responsible for the treatment of sewage from all of Sunnyvale and a small area inside the cities of Cupertino and San Jose. Named the “Sunnyvale Cleanwater Program” (Program), current cost estimates for Phases 1-3 of this Program are approximately $500 million over twenty years. The WPCP Master Plan was developed as a long-term guide for replacing facilities at the WPCP. The City adopted the Master Plan on August 23, 2016 (RTC No. 16-0663).

 

During Phase 1 of the Program, City staff identified that favorable financing was available for the Headworks and Primary Treatment Project through the State of California Clean Water State Revolving Fund (CWSRF). By securing this financing, the City can reduce debt service for the City’s Wastewater Management Fund by more than $47 million, compared to the default assumption of standard utility revenue bond financing.

 

Currently, the Program is beginning Phase 2 projects and is now in preliminary design for the Secondary Treatment and Dewatering Facilities Project (Project). The Project will replace the City's current secondary treatment process with conventional activated sludge (CAS) facilities and construct a thickening and dewatering facility and support facilities.

 

The Council adopted a resolution enabling submittal of the CWSRF application. The City applied for the CWSRF loan in December 2018 (RTC No. 18-1089). In June 2021, the City was notified this project was selected for the Fiscal Year 2021-2022 CWSRF Fundable List. To secure this financing, Council must adopt a resolution, which is further described below.

 

EXISTING POLICY

Council Fiscal Policy 7.11 Enterprise Fund Policies, 1.1b.1 Capital improvements associated with the existing infrastructure of a utility should be primarily funded from two sources: rate revenue and debt financing.

 

Council Fiscal Policy 7.11 Enterprise Fund Policies, 1.1b.3 Local, state, and federal funding sources, such as grants and contributions, should be pursued for utility-related capital improvement projects consistent with City priorities.

 

DISCUSSION

 

Execution of the State of California Clean Water State Revolving Fund Loan

The State Division of Financial Assistance administers the implementation of the State Water Board’s financial assistance programs, which include loan and grant funding for construction of municipal sewage and water recycling facilities. The CWSRF Program provides low-interest loans (approximately 2%) for a term of 30 years for water quality improvement projects. In 2016, the City applied for and received a CWSRF loan for the Program’s first phase, the Headworks and Primary Treatment Project. In 2021, the City was notified that it was also selected for a CWSRF loan for the second package of the Secondary Treatment and Dewatering Facilities Project.

 

This new CWSRF loan would finance permitting, design, and construction for the second package in Project 833210-SCWP Secondary Treatment Improvements-Split Flow CAS Stage 1. It would also some soft costs budgeted under Projects 833110-SCWP Oversight, 831470-SCWP Construction Management, and 830240-SCWP Program Management. Due to recent volatility in both the local construction market and the global supply chain, staff requested a 33% increase in the maximum loan amount, from $216 to $288 million. The State indicated that they will likely grant this request. 

 

To execute the loan, the City must submit a closing resolution adopted by the City Council. This Resolution approves the Installation Sale Agreement (“Financing Agreement”) on file with the State Water Board Office of the Manager and authorizes and directs the City Manager to execute and deliver the Financing Agreement.

 

Adopting this Resolution does not commit the City to executing the Financing Agreement. After the Project was selected for a CWSRF loan, the Build America, Buy America Act (BABA) was signed into law. This law imposes far-reaching domestic procurement requirements on infrastructure projects that receive federal funding after May 14, 2022. The U.S. Environmental Protection Agency (EPA) has indicated likely availability of waivers during the adjustment period, to cover projects designed prior to BABA. If such a waiver is not available, altering the Project to exclude foreign equipment and material could substantially impact cost and schedule.  After EPA promulgates detailed BABA requirements and issues general applicability waivers, the City Manager will verify that the requirements are consistent with Project goals before executing the Financing Agreement.

It is also important to note that the City issued bonds for improvements to the wastewater system in 2010, which were advance refunded in 2017. As part of that issuance, future state loans were contemplated and can be issued on parity (meaning the new debt will not be senior to the old) with the City’s 2017 Wastewater Refunding Bonds. In 2020, the City secured a Water Infrastructure Finance and Innovation Act (WIFIA) loan, through the U.S. Environmental Protection Agency, for over $220 million. That WIFIA loan, issued on parity, funds 49% of the Phase 2 Program. The new CWSRF loan would contribute to the 51% of the Phase 2 costs not covered by the WIFIA loan.

 

FISCAL IMPACT

There is no fiscal impact from adopting this Resolution. Budget for the project is included in the Wastewater Management Fund long-term financial plan. It is anticipated that even in the current escalating rate environment, the very low rates obtainable through CWSRF have the potential to save the City’s rate payers tens of millions dollars over the life of the loan when compared to a traditional public market financing. Taking this approach is the lowest cost option for financing this project. Additionally, as the program has become more tightly defined through validation, the projected cost has been adjusted upwards. Use of this cheaper financing alternative will help to mitigate the impact on rate payers.

 

PUBLIC CONTACT

Public contact was made by posting the Council agenda on the City's official-notice bulletin board outside City Hall, at the Sunnyvale Public Library and in the Department of Public Safety Lobby. In addition, the agenda and report are available at Office of the City Clerk, and on the City's website.

 

RECOMMENDATION

Recommendation

Adopt Resolution Authorizing the City Manager to Execute and Deliver an Installment Sale Agreement, for up to $288,000,000 in Clean Water State Revolving Funds, Between the City of Sunnyvale and the State Resources Water Control Board, and to Execute All Implementing Documents for Financial Assistance in Connection with the City’s Water Pollution Control Plant Update Project.

 

Staff

Prepared by: Allison Boyer, Assistant City Engineer, Public Works Department

Reviewed by: Chip Taylor, Director, Public Works Department

Reviewed by: Tim Kirby, Director of Finance

Reviewed by: Jacqueline Guzman, Deputy City Manager

Approved by: Kent Steffens, City Manager

 

 

ATTACHMENTS  

1. Resolution