File #: 24-0777   
Type: Report to Council Status: Consent Calendar
Meeting Body: City Council
On agenda: 7/23/2024
Title: Award of Contract in the Amount of $691,920 to Vellutini Corporation DBA Royal Electric Company for SMaRT Station NexGen Electrical Upgrade (PW24-20) and Finding of California Environmental Quality Act (CEQA) Categorical Exemption Pursuant to CEQA Guidelines Section 15301(a)
Attachments: 1. Bid Summary, 2. Draft General Construction Contract, 3. Budget Project Summary Sheets
REPORT TO COUNCIL

SUBJECT
Title
Award of Contract in the Amount of $691,920 to Vellutini Corporation DBA Royal Electric Company for SMaRT Station NexGen Electrical Upgrade (PW24-20) and Finding of California Environmental Quality Act (CEQA) Categorical Exemption Pursuant to CEQA Guidelines Section 15301(a)

Report
STAFF RECOMMENDATION
Recommendation
Take the following actions:
- Award a contract in substantially the same form as Attachment 2 to the report in the amount of $691,920 to Vellutini Corporation DBA Royal Electric Company of Sacramento, CA;
- Approve a 15% construction contingency in the amount of $103,788;
- Authorize the City Manager to execute the contract when all necessary conditions have been met; and
- Make a finding of a categorical exemption from the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301(a).

Report
BASIS FOR RECOMMENDATION
The SMaRT Station NexGen Electrical Upgrade Project (Project No. PR-23-01) is the first phase of a larger effort to upgrade the sorting and recycling equipment at the SMaRT Station. It is necessary to provide additional electrical capacity within the facility to power future equipment. The scope of work includes re-purposing an existing office to a new electrical room and installing a new electrical service consisting of a new switchboard, a new concrete equipment pad, new conduit and trenching, and all associated architectural, structural, and electrical work. The project will also improve accessibility in the existing parking lot.
The SMaRT Station NexGen Electrical Upgrade Project (Project No. PR-23-01) was advertised on Demandstar on May 24, 2024. Twenty-Six (26) contractors requested bid documents. Sealed bids were opened on June 12, 2024, with four (4) responsive bids received. Vellutini Corporation DBA Royal Electric Company submitted the lowest responsive and responsible bid in the amount of $691,920 (Attachment 1- Bid Summary). With the activities noted above as ...

Click here for full text