Award of Consultant Services Agreement with a Contract Amount Not-to-Exceed $831,398 to BKF Engineers for Evelyn Avenue Multi-Use Trail Project (F23-173) and Find the Project is Exempt from the California Environmental Quality Act (CEQA) Pursuant to CEQA Guidelines Section 15378 (a)
Report
STAFF RECOMMENDATION
Recommendation
Take the following actions:
- Award a Consultant Services Agreement in substantially the same form as Attachment 1 to the report in an amount not-to-exceed $831,398 to BKF Engineers of San Jose;
- Approve a 10% contingency in the amount of $83,140;
- Authorize the City Manager to execute the contract when all necessary conditions have been met; and
- Find the Project exempt from CEQA pursuant to CEQA Guidelines Section 15378 (a).
Report
BASIS FOR RECOMMENDATION
A request for proposals (RFP) was posted on DemandStar on July 18, 2023 and distributed to multiple California firms. Four (4) proposals were received on August 15, 2023. BKF Engineers was selected as the highest-ranked proposer. A detailed scope of work is included in Attachment 1 to this report.
ENVIRONMENTAL REVIEW
This award is for design and construction support services; therefore, the action being considered does not constitute a "project" within the meaning of the California Environmental Quality Act ("CEQA") pursuant to CEQA Guidelines section 15378(a) as it has no potential for resulting in either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment.
As part of the contract, the consultant will evaluate the project improvements and provide the City with a recommendation on how best to complete CEQA approval for the project improvements. The consultant's initial review of the project is that it is exempt under Public Resources Code Section 21080.20. The confirmation of applicable CEQA exemptions and the preparation of necessary CEQA clearance documentation are included in ...