Legislative Public Meetings

File #: 21-0133   
Type: Report to Council Status: Passed
Meeting Body: City Council
On agenda: 1/26/2021
Title: Award of Bid No. PW21-05 to DeSilva Gates Construction LP for Pavement Rehabilitation 2020 and Finding of California Environmental Quality Act (CEQA) Categorical Exemption
Attachments: 1. Bid Summary, 2. Draft General Construction Contract, 3. Project Summary Sheet, 4. List of Street Segments

REPORT TO COUNCIL

SUBJECT

Title

Award of Bid No. PW21-05 to DeSilva Gates Construction LP for Pavement Rehabilitation 2020 and Finding of California Environmental Quality Act (CEQA) Categorical Exemption

 

Report

STAFF RECOMMENDATION

Recommendation

-                     Make a finding of categorical exemption from the California Environmental Quality Act pursuant to California Environmental Quality Act Guidelines Section 15301(c),

-                     Award a contract in substantially the same form as Attachment 2 to the report in the amount of $2,719,415 to DeSilva Gates Construction LP,

-                     Authorize the City Manager to execute the contract when all necessary conditions have been met, and

-                     Approve a 10% contingency in the amount of $271,941.

 

Report

BASIS FOR RECOMMENDATION

The construction project was advertised on DemandStar on October 16. Twenty-five (25) contractors requested bid documents and sealed bids were opened on November 12, with nine (9) responsive bids received. DeSilva Gates Construction LP submitted the lowest responsive and responsible bid in the amount of $2,719,415 (Attachment 1 - Bid Summary).

 

ENVIRONMENTAL REVIEW

The proposed project is categorically exempt from environmental review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301(c) for the restoring and rehabilitating of existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities, involving negligible or no expansion of use beyond that presently existing.

 

FISCAL IMPACT

Funding is available in capital project 825290 - Pavement Rehabilitation, and Projects 831550, and 831680 which fund the adjustment of the utility infrastructure from the Water and Wastewater Funds (Attachment 3).

 

PUBLIC CONTACT

Public contact was made by posting the Council agenda on the City's official-notice bulletin board outside City Hall, Sunnyvale Public Library and Department of Public Safety. In addition, the agenda and report are available at the Office of the City Clerk and on the City's website.

 

Staff

Approved by: Kent Steffens, City Manager

 

ATTACHMENTS

1.                     Bid Summary

2.                     Draft General Construction Contract

3.                     Project Sheets 825290, 831550, and 831680

4.                     List of Street Segments