Title: Award of Contract to Graham Contractors, Inc. in the Amount of $781,840.41 for Slurry Seal 2024 B-SB1 Project No. ST-23-07 and Finding of Categorical Exemption from the California Environmental Quality Act (CEQA) Pursuant to CEQA Guidelines Section 15301(c)
Attachments: 1. Bid Summary, 2. Draft General Construction Contract, 3. Project 825290 - Slurry Seal Budget Summary Sheet, 4. Slurry Seal Locations, 5. Streets Map
REPORT TO COUNCIL

SUBJECT
Title
Award of Contract to Graham Contractors, Inc. in the Amount of $781,840.41 for Slurry Seal 2024 B-SB1 Project No. ST-23-07 and Finding of Categorical Exemption from the California Environmental Quality Act (CEQA) Pursuant to CEQA Guidelines Section 15301(c)

Report
REPORT IN BRIEF
Approval is requested to award a construction contract in substantially the same form as Attachment 2 to this report, in the amount of $781,840.41 to Graham Contractors, Inc. of San Jose for Slurry Seal 2024 B-SB1, and approval of a 10% construction contingency in the amount of $78,184.

EXISTING POLICY
Pursuant to Section 2.09.040 of the Sunnyvale Municipal Code, City Council approval is required for awards of public works contracts exceeding $250,000.

Pursuant to Section 2.09.140(b) of the Sunnyvale Municipal Code, the City Council may reject bids or proposals received in response to formal competitive bid solicitations.

ENVIRONMENTAL REVIEW
This project is exempt under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301(c), for the repair, maintenance, or minor alteration of existing facilities, including highways, streets and similar facilities, involving negligible or no expansion of use beyond that which presently exists.

BACKGROUND AND DISCUSSION
The Slurry Seal 2024 B-SB1 Project (Public Works Project No. ST-23-07) consists of the installation of slurry seal along portions of Hollenbeck Avenue, Arques Avenue, and Morse Avenue (see Attachment 5 to the report). This Project also includes installing thermoplastic pavement striping, markings, legends, green bike lanes and raised pavement markers.

An invitation for bids was posted on the City's DemandStar public procurement network, distributed to local Bay Area Builder's Exchanges, and published on the City's website on January 12, 2024. Twenty-three (23) contractors requested bid documents with six (6) sealed bids publicly opened on January 31, 2024. Graha...