Legislative Public Meetings

File #: 20-0763   
Type: Report to Board/Commission Status: Passed
Meeting Body: Planning Commission
On agenda: 10/26/2020
Title: Proposed Project: PEERY PARK PLAN REVIEW PERMIT to construct two five-story office/R&D buildings totaling 391,131 square feet in floor area and 100% floor area ratio (FAR), and a six-level parking structure. Location: 888 Ross Drive (APNs: 110-07-035, 036) File #: 2019-7860 Zoning: Peery Park Specific Plan/Innovation Edge (PPSP/IE) Applicant / Owner: Perry Hariri / STP Property LLC Environmental Review: The project is exempt from CEQA review pursuant to CEQA Guidelines Section15168 (c)(2) and Public Resources Code Section 21094 (c). The project is within the scope of the Peery Park Specific Plan Program EIR as no new environmental impacts are anticipated and no new mitigations are required. Project Planner: Margaret Netto, (408) 730-7628, mnetto@sunnyvale.ca.gov
Attachments: 1. Reserved for Report to Council, 2. Vicinity Map, 3. Project Data Table, 4. Recommended Findings, 5. Standard Requirements and Recommended COAs, 6. CEQA Checklist for PPSP EIR Compliance, 7. PPSP EIR-MMRP for Project, 8. Proposed Community Benefits Plan, 9. Site and Architectural Plans, 10. ALUC Consistency Determination, 11. Arborist Report, 12. Links to Draft and Final EIR for PPSP, 13. Landscape Plans, 14. Staff Presentation 20201026 (20-0763)
Related files: 20-0941
REPORT TO PLANNING COMMISSION
SUBJECT
Title
Proposed Project: PEERY PARK PLAN REVIEW PERMIT to construct two five-story office/R&D buildings totaling 391,131 square feet in floor area and 100% floor area ratio (FAR), and a six-level parking structure.
Location: 888 Ross Drive (APNs: 110-07-035, 036)
File #: 2019-7860
Zoning: Peery Park Specific Plan/Innovation Edge (PPSP/IE)
Applicant / Owner: Perry Hariri / STP Property LLC
Environmental Review: The project is exempt from CEQA review pursuant to CEQA Guidelines Section15168 (c)(2) and Public Resources Code Section 21094 (c). The project is within the scope of the Peery Park Specific Plan Program EIR as no new environmental impacts are anticipated and no new mitigations are required.
Project Planner: Margaret Netto, (408) 730-7628, mnetto@sunnyvale.ca.gov

Report
REPORT IN BRIEF
General Plan: Peery Park Specific Plan (PPSP)
Existing Site Conditions: Existing one and two-story office/R&D buildings
Surrounding Land Uses
North: Freeway (State Route 237)
South: Freeway (U.S. Highway 101)
East: Office/R&D, Year Round Homeless Shelter, and two hotels
West: Freeways 237 and 101
Issues: Implementation of the PPSP and tree removals
Staff Recommendation: Alternative 1: Recommend that the City Council make the required Findings to approve the CEQA determination that the project is exempt from CEQA review pursuant to CEQA Guidelines Section 15168 (c)(2) and Public Resources Code Section 21094 (c) as it is within the scope of the Peery Park Specific Plan (PPSP) Environmental Impact Report (EIR) and no additional environmental review is required in Attachment 6; make the Findings for the Peery Park Plan Review Permit, and Sense of Place Fee in Attachment 4; and approve the Peery Park Plan Review Permit subject to the PPSP Mitigation Monitoring and Reporting Program in Attachment 7 and recommended conditions of approval noted in Attachment 5.

BACKGROUND
Description of Proposed Project
The project includes ...

Click here for full text